Time
Management
| Not
a
Member Yet? The Mind Tools Career Excellence Club gives
you the training, coaching and support you need to make a lasting
success of your career. Take our FREE tour, and find out what it can
do for you!
Recent Discussions:
Quick Start
Relevant
Courses & Resources
|
Critical Path Analysis and
|
Task |
Possible start | Length | Type | Dependent on... |
1. High level analysis |
week 1 | 5 days | sequential | |
2. Selection of hardware platform |
week 1 | 1 day | sequential | 1 |
3. Installation and commissioning of hardware |
week 3 | 2 weeks | parallel | 2 |
|
4. Detailed analysis of core modules |
week 1 | 2 weeks | sequential | 1 |
5. Detailed analysis of supporting utilities |
week 1 | 2 weeks | sequential | 4 |
6. Programming of core modules |
week 4 | 3 weeks | sequential | 4 |
7. Programming of supporting modules |
week 4 | 3 weeks | sequential | 5 |
8. Quality assurance of core modules |
week 5 | 1 week | sequential | 6 |
9. Quality assurance of supporting modules |
week 5 | 1 week | sequential | 7 |
10.Core module training |
week 7 | 1 day | parallel | 6 |
11.Development of accounting reporting |
week 6 | 1 week | parallel | 5 |
12.Development of management reporting |
week 6 | 1 week | parallel | 5 |
13.Development of management analysis |
week 6 | 2 weeks | sequential | 5 |
14.Detailed training |
week 7 | 1 week | sequential | 1-13 |
15.Documentation |
week 4 | 2 weeks | parallel | 13 |
2. Plot the activities as a circle and arrow
diagram
Critical Path Analyses are presented using circle and arrow diagrams.
In these, circles show events within the project, such as the start and finish of tasks. Circles are normally numbered to allow you to identify them.
An arrow running between two event circles shows the activity needed to complete that task. A description of the task is written underneath the arrow. The length of the task is shown above it. By convention, all arrows run left to right.
An example of a very simple diagram is shown below:

This shows the start event (circle 1), and the completion of the 'High Level Analysis' task (circle 2). The arrow between them shows the activity of carrying out the High Level Analysis. This activity should take 1 week.
Where one activity cannot start until another has been completed, we start the arrow for the dependent activity at the completion event circle of the previous activity. An example of this is shown below:

Here the activities of 'Selecting Hardware' and 'Core Module Analysis' cannot be started until 'High Level Analysis' has been completed. This diagram also brings out a number of other important points:
A different case is shown below:

Here activity 6 to 7 cannot start until the other three activities (12 to 6, 5 to 6 and 9 to 6) have been completed.
See figure 5 for the full circle and arrow diagram for the computer
project we are using as an example.
Click here to see the full Critical Path Diagram
This shows all the activities that will take place as part of the project. Notice that each event circle has a figure below it as well as a figure above. This shows the latest time that it can be reached with the project still being completed in the minimum time possible. You can calculate this by starting at the last event (in this case number 7), and working backwards.
You can see that event 4 can be completed any time between 1.2 weeks in and 7.8 weeks in. The timing of this event is not critical. Events 1 to 2, 2 to 3, 3 to 4, 4 to 5, 5 to 6 and 6 to 7 must be started and completed on time if the project is to be completed in 10 weeks. This is the 'critical path' - these activities must be very closely managed to ensure that activities are completed on time. If jobs on the critical path slip, immediate action should be taken to get the project back on schedule. Otherwise completion of the whole project will slip.
You may find that you need to complete a project earlier than your Critical Path Analysis says is possible. In this case you need to take action to reduce the length of time spent on project stages.
You could pile resources into every project activity to bring down time spent on each. This would probably consume huge additional resources.
A more efficient way of doing this would be to look only at activities on the critical path.
As an example, it may be necessary to complete the computer project in figure 5 in 8 weeks rather than 10 weeks. In this case you could look at using two analysts in steps '2 to 3' and '3 to 4', and two programmers instead of one in step '4 to 5'. This would shorten the project by two weeks, but would raise the project cost - doubling resources at any stage often only improves productivity by, say, 50%. This occurs as time spent on coordinating the project consumes time gained by increasing resource.
Note that in this example, shortening the project by two weeks brings activities '3 to 11', '11 to 12' and '12 to 6' onto the critical path as well.
As with Gantt Charts, in practice project managers tend to use software tools like Microsoft Project to create CPA Charts. Not only do these ease make them easier to draw, they also make modification of plans easier and provide facilities for monitoring progress against plans. Microsoft Project is reviewed at the top of our left hand title bar.
PERT is a variation on Critical Path Analysis that takes a slightly more skeptical view of time estimates made for each project stage. To use it, estimate the shortest possible time each activity will take, the most likely length of time, and the longest time that might be taken if the activity takes longer than expected.
Use the formula below to calculate the time to use for each project stage:
shortest time + 4 x likely time + longest time
-----------------------------------------------------------
6
This helps to bias time estimates away from the unrealistically short time-scales normally assumed.
Critical Path Analysis is an effective and powerful method of assessing:
An effective Critical Path Analysis can make the difference between success and failure on complex projects. It can be very useful for assessing the importance of problems faced during the implementation of the plan.
PERT is a variant of Critical Path Analysis that takes a more skeptical view of the time needed to complete each project stage.
MindTools.com - Join Our Community!
In the next article, we look at the Planning Cycle, a planning process for middle-sized projects. To read this, click 'Next article' below. Other relevant destinations are shown in the "Where to go from here" list underneath.
| |
| Where to go from here: | |
Join Mind Tools | |
Free Newsletter |
| Download & Print | |
Next Article |
Work Breakdown Structures - Mapping out the work within a project*
Project Dashboards - Quickly communicating project progress*
Project Initiation Documents - Getting your project off to a great start
Project Milestone Reporting - Keeping projects on track by monitoring check points*
Plan-Do-Check-Act (PDCA) - Implementing new ideas in a controlled way*
Logframes, and the Logical Framework Approach - Planning projects robustly
A full list of Mind Tools articles is available here.
Learn to manage the stress in your life with our sister site, stress.mindtools.com.
Mind Tools Store: Mind Tools Ebook, Make Time for Success
Stress Management Masterclass, How to Lead, Design Your Life
Relaxation MP3s
© Mind Tools Ltd, 1995-2008, All Rights Reserved
For requests to reprint or reproduce material from this site, please contact our Permissions Center.
Store · Search · Newsletter · Downloads · Advertisers · Affiliates
MindTools.com is one of the Internet's most-visited career skills resources.
Click here to see analysis.
"All I can say is WOW! This is one of the best managerial tool sites I have encountered. It is nice to find pertinent material in such volumes, and that is SO EASY to read and understand."
Marianne Darden,
RN, MSN, MS,
CNOR, CNA, CLNC
"Of all the sites that I have visited on the net, this is the most exciting and useful so far. I am so happy that I discovered it. Keep up the very beautiful work that you are doing."
Caleb Muchungu,
Malawi
"I have used many of your ebooks and downloads for the past couple of years and continue to gain great insight into helping me develop my own as well as other peoples skills... My most sincere thanks to you and your team for helping me reach my true potential."
David Snelders,
Leicester, UK.