Time
Management
|
Useful Links
Not
a
Member Yet? The Mind Tools Career Excellence Club gives
you the training, coaching and support you need to make a lasting
success of your career. Take our FREE tour, and find out what it can
do for you!
Recent Discussions:
Quick Start
Relevant
Courses & Resources
|
Critical Path Analysis
|
Task |
Earliest start |
Length |
Type |
Dependent on... |
A. High level analysis |
Week 0 |
1 week |
Sequential |
|
B. Selection of hardware platform |
Week 1 |
1 day |
Sequential |
A |
C. Installation and commissioning of hardware |
Week 1.2 |
2 weeks |
Parallel |
B |
D. Detailed analysis of core modules |
Week 1 |
2 weeks |
Sequential |
A |
E. Detailed analysis of supporting modules |
Week 3 |
2 weeks |
Sequential |
D |
F. Programming of core modules |
Week 3 |
2 weeks |
Sequential |
D |
G. Programming of supporting modules |
Week 5 |
3 weeks |
Sequential |
E |
H. Quality assurance of core modules |
Week 5 |
1 week |
Sequential |
F |
I. Quality assurance of supporting modules |
Week 8 |
1 week |
Sequential |
G |
J.Core module training |
Week 6 |
1 day |
Parallel |
C,H |
K. Development and QA of accounting reporting |
Week 5 |
1 week |
Parallel |
E |
L. Development and QA of management reporting |
Week 5 |
1 week |
Parallel |
E |
M. Development of Management Information System |
Week 6 |
1 week |
Sequential |
L |
N. Detailed training |
Week 9 |
1 week |
Sequential |
I, J, K, M |
Step 2. Plot the activities as a circle and arrow
diagram
Critical Path Analyses are presented using circle and arrow diagrams.
In these, circles show events within the project, such as the start
and finish of tasks. The number shown in the left hand half of the circle allows you to identify each one easily. Circles are sometimes known as nodes.
An arrow running between two event circles shows the activity needed
to complete that task. A description of the task is written
underneath the arrow. The length of the task is shown above it. By
convention, all arrows run left to right. Arrows are also sometimes called arcs.
An example of a very simple diagram is shown below:

This shows the start event (circle 1), and the
completion of the 'High Level Analysis' task (circle 2). The arrow
between them shows the activity of carrying out the High Level
Analysis. This activity should take 1 week.
Where one activity cannot start until another has been completed, we
start the arrow for the dependent activity at the completion event
circle of the previous activity. An example of this is shown below:

Here the activities of 'Select Hardware' and 'Core Module Analysis' cannot be started until 'High Level Analysis' has been completed. This diagram also brings out a number of other important points:
A different case is shown below:

Here activity 6 to 7 cannot start until the other
four activities (11 to 6, 5 to 6, 4 to 6, and 8 to 6) have been completed.
Click the link below for the full circle and arrow diagram for the computer
project we are using as an example.
Figure 5: Full Critical Path Diagram
This shows all the activities that will take
place as part of the project. Notice that each event circle also has a
figure in the bottom, right hand quadrant. This shows the latest finish time that's permissible for the preceding activity if the project is to be completed in the minimum time possible. You can calculate this by starting at the last
event and working backwards.The latest finish time of the preceding event and the earliest start time of the following even will be the same for circles on the critical path.
You can see that event M can start any time between weeks
6 and 8. The timing of this event is not critical. Events
1 to 2, 2 to 3, 3 to 4, 4 to 5, 5 to 6 and 6 to 7 must be started and
completed on time if the project is to be completed in 10 weeks. This
is the 'critical path' – these activities must be very closely
managed to ensure that activities are completed on time. If jobs on
the critical path slip, immediate action should be taken to get the
project back on schedule. Otherwise completion of the whole project
will slip.
You may find that you need to complete a project earlier than your Critical Path Analysis says is possible. In this case you need to re-plan your project.
You have a number of options and would need to assess the impact of each on the project’s cost, quality and time required to complete it. For example, you could increase resource available for each project activity to bring down time spent on each but the impact of some of this would be insignificant and a more efficient way of doing this would be to look only at activities on the critical path.
As an example, it may be necessary to complete the computer project in Figure 5 in 8 weeks rather than 10 weeks. In this case you could look at using two analysts in activities 2 to 3 and 3 to 4. This would shorten the project by two weeks, but may raise the project cost – doubling resources at any stage may only improve productivity by, say, 50% as additional time may need to be spent getting the team members up to speed on what is required, coordinating tasks split between them, integrating their contributions etc.
In some situations, shortening the original critical path of a project can lead to a different series of activities becoming the critical path. For example, if activity 4 to 5 were reduced to 1 week, activities 4 to 8 and 8 to 6 would come onto the critical path.
As with Gantt Charts, in practice project managers use
software tools like Microsoft Project to create CPA Charts. Not only
do these ease make them easier to draw, they also make modification
of plans easier and provide facilities for monitoring progress
against plans.
PERT is a variation on Critical Path Analysis that takes a slightly
more skeptical view of time estimates made for each project stage. To
use it, estimate the shortest possible time each activity will take,
the most likely length of time, and the longest time that might be
taken if the activity takes longer than expected.
Use the formula below to calculate the time to use for each project
stage:
shortest time + 4 x likely time + longest time
-----------------------------------------------------------
6
This helps to bias time estimates away from the unrealistically short time-scales normally assumed.
Critical Path Analysis is an effective and powerful method of assessing:
An effective Critical Path Analysis can make the difference between
success and failure on complex projects. It can be very useful for
assessing the importance of problems faced during the implementation
of the plan.
PERT is a variant of Critical Path Analysis that takes a more
skeptical view of the time needed to complete each project stage.
MindTools.com - Join Our Community!
The next article in this section looks at the LogFrame Approach - a useful way of checking that your projects have logical integrity. To read this, click "Next Article" below.
|
Was this article helpful? |
|
| |
| Where to go from here: | |
Join Mind Tools | |
Free Newsletter |
| Download & Print | |
Next Article |
Work Breakdown Structures – Mapping out the work within a project*
Project Dashboards – Quickly communicating project progress*
Project Initiation Documents – Getting your project off to a great start
Project Milestone Reporting – Keeping projects on track by monitoring check points*
Plan-Do-Check-Act (PDCA) – Implementing new ideas in a controlled way*
Logframes, and the Logical Framework Approach – Planning projects robustly
A full list of Mind Tools articles is available here.
Learn to manage the stress in your life with our sister site, stress.mindtools.com.
Online Training
Mind Tools Store: Mind Tools Ebook, Make Time for Success
Stress Management Masterclass, How to Lead
Relaxation MP3s
© Mind Tools Ltd, 1995-2010, All Rights Reserved
We welcome appropriate reprinting and reuse of Mind Tools material,
however, you must
get our permission first!
To do this, please visit our Permissions Center.
Store · Search · Newsletter · Downloads · Advertisers · Affiliates
MindTools.com is one of the Internet's most-visited career skills resources.
Click here to see analysis.
"All I can say is WOW! This is one of the best managerial tool sites I have encountered. It is nice to find pertinent material in such volumes, and that is SO EASY to read and understand."
Marianne Darden,
RN, MSN, MS,
CNOR, CNA, CLNC
"Of all the sites that I have visited on the net, this is the most exciting and useful so far. I am so happy that I discovered it. Keep up the very beautiful work that you are doing."
Caleb Muchungu,
Malawi
"I have used many of your ebooks and downloads for the past couple of years and continue to gain great insight into helping me develop my own as well as other peoples skills... My most sincere thanks to you and your team for helping me reach my true potential."
David Snelders,
Leicester, UK.