Post-Implementation Reviews
Making Sure that What You Delivered Actually Works
"Lessons learned...
and more."
© iStockphoto
"Completing a project" is not the same thing as ending the
project management process. Simply finishing doesn't ensure that
the organization benefits from the project's outcome.
For example, after completing a year long project to establish a
new quality management process for your organization, you want to make
sure that what you set out to do was actually achieved. Your
objective wasn't to simply deliver a process – but rather, to
deliver the process that addresses the specific business need you
intended to meet. This is the real measure of success.
To make the most of the benefits that the project can deliver, however, you
also need to check to see if further improvements will deliver still
greater benefit.
You also need to ensure that the lessons learned during the
project are not forgotten. You can more effectively design and
execute future projects when you take advantage of lessons learned
through experience of previous projects.
So how can you properly measure a project's success, and work
toward continuous improvement? This is where the process of
Post-Implementation Review (PIR) is helpful. It helps you answer
the following key questions:
- Did the project fully solve the problem that it was designed to
address?
- Can we take things further, and deliver even bigger benefits?
- What lessons did we learn that we can apply to future projects?
The PIR Process
The key to a successful PIR is recognizing that the time spent on
the project is just a small part of an ongoing time-line.
For
people and organizations that will be working on similar projects
in the future, it makes sense to learn as many lessons as
possible, so that mistakes are not repeated in future projects.
And for organizations benefiting from the project, it makes sense
to ensure that all desired benefits have been realized, and to understand what additional benefits can be achieved.
When to Review
A good time to start thinking about the Post Implementation Review is when members of the project team
remember the most – shortly after the project has been delivered,
and when most of the problems have been ironed-out. Start to list ideas and observations while they are still fresh in people's minds.
However, to adequately assess the quality of the implementation and complete this process, you'll need to wait long
enough for the changes caused by the project to truly take effect.
There will probably be a period of adjustment before you can
finally review the solution as it was intended to operate: you'll
likely need to overcome some of the usual resistance to change,
hold people's hands while they operate new systems, and eliminate
technical problems that didn't emerge when deliverables were
tested. You should therefore typically allow a few weeks, or even
a few months, before doing the full PIR. Where possible,
allow for at least one, full, successful cycle of business before reviewing lessons learned.
What to Review
Here are some tips for conducting the PIR:
- Ask for openness – Emphasize the importance of being open and
honest in your assessment, and make sure that people aren't in any
way punished for being open.
- Be objective – Describe what has happened in objective terms, and
then focus on improvements.
- Document success – Document practices and procedures that led to
project successes, and make recommendations for applying them to
similar future projects.
- Look with hindsight – Pay attention to the "unknowns" (now
known!) that may have increased implementation risks. Develop a
way of looking out for these in future projects.
- Be future-focused – Remember, the purpose is to focus on the
future, not to assign blame for what happened in the past. This is
not the time to focus on any one person or team.
- Look at both positives and negatives – Identify positive as well
as negative lessons.
When conducting the review, include the following activities:
- Conduct a gap analysis.
- Review the project charter to evaluate how closely the project
results match the original objectives.
- Review the expected deliverables (including documentation) and ensure either that these have been delivered to an acceptable level of quality, or that an acceptable substitute is in place.
- If there are gaps, how will these be closed?
- Determine whether the project goals were achieved.
- Is the deliverable functioning as expected?
- Are error rates low enough, and is it fit for purpose?
- Is it functioning well, and in a way that will adjust smoothly to future operating demands?
- Are users adequately trained and supported? And are there sufficiently enough confident, skilled people in place?
- Are the necessary controls and systems in place, and are they working
properly?
- What routine activities are needed to support the project's
success?
- If there are problems here, how will these be addressed?
- How does the end result compare with the original project plan, in terms of quality, schedule and budget?
- Determine the satisfaction of stakeholders.
- Were the end users' needs met?
- Is the project sponsor satisfied?
- What are the effects on the client or end user?
- If key individuals aren't satisfied, how should this be addressed?
- Determine the project's costs and benefits.
- What were the final costs?
- What will it cost to operate the solution?
- What will it cost to support the solution in the future?
- How do the costs compare with the benefits achieved?
- If the project hasn't delivered a sufficiently large return, how can this be improved?
- Identify areas of further development.
- Have all of the expected benefits been achieved? If not, what is needed to achieve them?
- Are there opportunities for further training and coaching that
will maximize results?
- Could you make further changes, which would deliver even more value?
- Are there any other additional benefits that can be achieved?
- Identify lessons learned.
- How well were the projects deliverables assessed, and how well were timescales and costs assessed?
- What went wrong, why did these things go wrong, and how could these problems be avoided next time?
- What went well, and needs to be learned from?
- Report findings and recommendations.
- What have you learned from this review?
- Do you need corrective activity to get the benefits you want?
- What lessons have you learned that need to be carried forward to future projects?
- Does this project naturally lead on to future projects, which will
build on the success and benefits already achieved?
How to Review
As you perform the post-implementation review, certain methods and
practices will help you obtain the best possible information:
- Define the scope of the review beforehand -The last thing you
want to do is to create a political problem. Given the number of people
often involved in a project, it's easy to hurt someone's feelings
when reviewing the project's success. Clarify your objectives for
the review, and make your intentions clear – this will better
ensure that people share their experiences openly and honestly. Then make absolutely sure that you stick to these intentions, and that people's egos aren't unnecessarily bruised by the process!
- Review key documents – Gather together the key project
documents. This will help you assess the project planning process,
as well as the actual benefits achieved through the project.
- Consider using independent reviewers – Where possible, use
outside people in your review process to get an objective,
unclouded view of the project. Some people recommend using only
independent people in the review, however, you can learn a lot
from the perspectives of those who were directly involved in the
project – this is why the best strategy is probably to have a
balance.
- Use appropriate data collection – Collect information in the
most appropriate way, for example, by using interviews and
surveys. Also, test the deliverable yourself, to make sure you get
firsthand information.
- Deliver appropriate reports – Report your findings, and
publicize the results. Remember that the PIR is designed to help
project managers conduct more effective projects in the future, as
well as to measure and optimize the benefits of the specific
project being reviewed.
- Present recommendations – Present the detailed recommendations
to the organization and the project leaders, as well as to customers
and other stakeholders. Include as many people as necessary so
that you keep – and apply – the best-practice information in the
future.
As you plan your PIR, be aware of the
costs and benefits of the review process itself.
Interviewing stakeholders and customers, testing the
solution, and documenting the results are time-consuming
activities. Make sure the time and resources dedicated to
the review are consistent with the project scope and its
output, and that the potential benefits of conducting the
review are worth the effort put in.
Key Points
A Post-Implementation Review (PIR) is conducted after completing
a project. Its purpose is to evaluate whether project objectives
were met, to determine how effectively the project was run, to
learn lessons for the future, and to ensure that the organization
gets the greatest possible benefit from the project.
After a long project, the last thing many project teams want to do
is relive the process and look for ways to improve. However, a
forward-looking review can discover many tips and strategies for
improvement.
By conducting a thorough and timely PIR, you'll identify key
lessons learned – and you can then apply those lessons to the
planning and management of future projects.
Join the Mind Tools Club
Get training, help and ideas to boost your career: the Mind Tools Club gives you much, much more than you get here on the basic Mind Tools site.
And if you join before midnight on May 9th, we'll also give you a FREE copy of our Future-Proof Your Career workbook.
Find out what you get
Where to go from here:
Next article 
Free newsletter 
Join Mind Tools 